26-21 Water Street Sewer Improvements Phase B - Hopkins Alley to Front Street (REJECTED)

ID: 26-21(R)

Title: 26-21 Water Street Sewer Improvements Phase B - Hopkins Alley to Front Street (REJECTED)

Bid Start Date: Sept. 4, 2026, 4 p.m.

Bid End Date: Sept. 30, 2026, 10 a.m.

Status: Closed - Award Pending

Active: True

Bid Opening Info: September 30, 2026 at 10:00 AM Alaska Time

Description:

NOTICE IS HEREBY GIVEN that the City of Ketchikan is requesting sealed bids for Water Street Sewer Improvements Phase B – Hopkins Alley to Front Street, Contract No. 26-21, consisting of furnishing all labor, equipment, materials, supervision, and other facilities necessary to complete the Work set forth in the Contract Drawings and Specifications, and terms of the Contract successfully.

The Work that is presented in the Bid Proposal for this Contract generally consists of 1,369 LF of 6 to 16-inch cured-in-place pipe (CIPP) lining, 93 LF of 6 to 16-inch C900 open cut replacement, rehabilitation/replacement of four manholes, installation of one force main bypass manhole, and associated cleaning, CCTV inspection, temporary bypass piping, excavation and backfill, asphalt paving and traffic control, complying with all State and Federal permits and coordinating work with the Owner.  The Contract Drawings further define the scope of work. 

This project has been funded wholly or in part by the Alaska Department of Environmental Conservation’s State Revolving Fund Program under Alaska Clean Water Fund (ACWF) loan number 481211-S.

Qualifications:

Special Requirements:

Misc. Info:

All documents that need to be submitted for bid are in '26-21 Bid Packet'

Engineers Estimate: $2,000,000 - $2,600,000

Pre-Bid meeting at the City of Ketchikan Public Works Administration Building, 2930 Tongass Ave, Ketchikan, Alaska 99901. Virtual attendance is permitted at:

Join: https://teams.microsoft.com/meet/262004465589714?p=ZOjwpPEZBbnAWpLCRk

Meeting ID: 262 004 465 589 714

Passcode: i8eV2Rs2

Addendum Date: Sept. 14, 2026, 2:30 p.m.

Pre Bid Meeting: September 21, 2026 at 1:00 PM Alaska Time

Contact Person:

Mark Barry

markbarry@ketchikan.gov

907-204-8504

Business Hours: 8:00AM - 5:00PM

Categories:

  • Engineering
  • Ketchikan Public Utilities (KPU)
  • Public Works
  • Street Maintenance
  • Waste Water
  • Water

Bid Documents

  • 26-21 Bid Packet.pdf
  • 26-21 Bid Tabulations.pdf
  • 26-21 Planset.pdf
  • 26-21 Contract Documents.pdf
  • 26-21 Addendum 1.pdf
  • 26-21 Addendum #2.pdf
  • 26-21 Pre-Bid Meeting Minutes 20260921.pdf
  • I-01 MH 20010313.pdf
  • I-03 TO I-01 2025 VIDEO.mp4
  • SS9 - 522 Water St Lateral 20260710.mp4
  • SS4 - 540 Water St Lateral 20260710.mp4
  • GS5 - C900Tunnel to MH I-03 20260206.mp4
  • I-04 TO H-05-2 20200624.MPG
  • I-04 TO H-05-2 20200624.pdf
  • I-04 TO I-03 20200625.MPG
  • I-04 TO I-03 20200625.pdf
  • 26-21 Addendum 3.pdf
  • 1950 Tongass Ave - Water St Improvement.pdf
  • Contract 78-A-2, Force & Gravity Mains Tremont to Mission.pdf
  • DOT&PF Project 68571 Viaducts Rehabilitation Stage II.pdf
  • DOT&PF Project 71111, Ketchikan Viaducts Rehabilitation.pdf
  • 260214 MH HH-1 to PS3.mp4

Plan Holders

First Name Last Name Company
Mary Ditz The Plans Room LLC
Jonathan Edmonson SmartProcure
Source Management Onvia
Mary Lamoreaux eRepublic, Inc.
Terra Sterlace Envirobidnet
Luke Bentley Dawson
Megan Verdoorn Plan Center Northwest
Karlee Miller proHNS LLC
Kira Bennett Dawson Construction, LLC
Tim McDonald Seattle DJC
Tina Spah Builders Exchange of Washington
AGC Plans AGC of Alaska
Brad Roberts Spray Glass
Siva Kumar VISUAL
Mark Thommasen Core and Main
Robyn Stevens Spokane Regional Plan Center
Robert Diaz
Mary Miller Pwxpress
Aidan Pace Impreg
Mark Barry
Josh Henrick sturgeon electric
Mike Redmond Construct Connect
Lloyd Coogan Coogan Const.Co,
Oscar Hopps Alaska C-Dive LLC
Ernest Hamilton Three Dog Construction Inc
Harold Enright Ketchikan ready mix
Jayalakshmi Loganathan Dodge Data & Analytics
Jim Swain CIP Construction
Nicholas Hebnes Frawner Corporation
Chris Rahr Pool Enginerring
Brett Serlin Tongass Engineering
Levi Wallace Dawson Construction LLC
Dodge Reports Dodge Data & Analytics
Kyle Heaton
Doug Suzuki Shoreline Construction Co.
Benjamin Davis proHNS